cement-epc

EPC projects’ management and operations.

What are the problems encountered in sand aggregate production line?

2019-10-16 16:47:15 | 日記
Product introduction:https://www.lvssn.com/epc/Aggregate-Production-Line.html


With the joining of cement enterprises, the appearance of sand aggregate industry is gradually developing to scale, environmental protection, ecology and sustainability.However, due to the diversity of raw materials and markets and the uneven level of design units, most production lines cannot fully achieve the original intention and purpose of the investors after being put into production, or there are various problems in the operation process.What are the problems encountered in sand aggregate production line?
 



1. Improper equipment selection




aggregate production line
 



Reasonable equipment selection is the primary factor to determine the success of a production line.Equipment selection of sand aggregate production line mainly depends on physical properties of raw materials (such as hardness, abrasion index of raw materials, soil content, etc.).Because there are many production line investors did not find a formal company design, by directly copying the equipment selection of other enterprises for construction, after the operation of the equipment selection is not reasonable.This problem is difficult to solve by adjusting the process, the production enterprises have to replace the extrusion crusher equipment to ensure the long-term stable and economic operation of the production line.Therefore in the choice of manufacturers must choose the strength of equipment manufacturers or formal company design production lines.Jiangsu LVSSN has a number of design lines, you are welcome to visit.
 



2. Improper design of silos or warehouses




aggregate production line
 



Silos or silos of sand aggregate production line mainly include coarse feed silos, medium and fine break and sand buffer silos and product storage warehouses.
 



(1) coarse feed bin




The common problem of coarse feeding bin is that the side discharge port of the bin is designed as a rectangular "door" structure. There is a dead Angle between the warehouse and the discharge port, material feeding is not smooth enough, and large pieces of material are easy to accumulate here, which affects the normal feeding.The simple measure to solve this problem is to place an excavator beside the feeding mouth to clean up the accumulated material at any time.In the off-season of the market, the feeding bin side outlet is transformed into a trapezoidal "inverted eight" structure, so as to eliminate the dead corner of the product.
 



(2) medium and fine crushing and sand making buffer bin




The common problem of medium fine breaking and sand making buffer bin is that the bottom of the bin is designed as a steel bin structure with flat bottom. Because the overall material pressure at the bottom of the bin is relatively large, serious deformation and subsidence of the bottom of the steel bin will occur during the operation of the sand and stone aggregate production line, resulting in safety risks.The improvement measures can be taken to strengthen the structure of the bottom of the warehouse.The design unit shall try to avoid the use of flat steel structure in the design, and try to choose concrete structure at the bottom of the flat steel structure when it is inevitable to choose flat steel structure.
 



(3) product repository




Product storage is generally in the form of concrete storage, with large and stable reserves. However, some enterprises choose steel silos to store sand and stone aggregates. It is hoped that these enterprises can regularly check the wear condition of steel silos and carry out wear resistance treatment.
 



3. Wear of material slide




aggregate production line
 



Due to the multi-edge and Angle characteristics of aggregate intermediate products, the high abrasion characteristics of some raw materials and the large delivery gap of some materials, the impact wear of most runways in the conveying process is serious and the service life is short.This problem can be improved by laying cast manganese steel or other material lining board inside the impact-heavy slide.Change the structure form of the slide with less impact, and form the abrasive material inside the slide, and thicken the slide steel plate under the condition of conditions.However, when conveying soil materials, it is recommended to adopt thickening treatment for the slide, and it is not necessary to adopt the design of abrasive ladder slide, because the structure of abrasive slide is easy to cause the clogging of soil materials on the slide.

The above is only a small part of the problems in the aggregate production line. If you encounter other problems in the aggregate production line, please contact us and we can propose solutions for you.




The page source:https://www.lvssn.com/Industry/What-are-the-problems-encountered-in-sand-aggregate-production-line.html

Jaw crusher stuck material solution

2019-10-16 16:44:13 | 日記
Product introduction:https://www.cementepc.net/crusher/Jaw-crusher.html


In the working process of jaw crusher, sometimes there will be stuck material can not be ore, directly affect the subsequent production.So, what are the reasons for jaw crusher stuck?What is the solution of jaw crusher stuck material?
 



1. The material has high water content or high viscosity




In the working process of jaw crusher, if the water content of the ore is higher, into the crushing chamber, containing water after the material is broken into small pieces, will mutually adhesion together, block in the crushing chamber of the two jaw plate directly, resulting in material jam.Or the material mixed with more viscous dilute soil, so that the material is stuck into a block of broken cavity, the phenomenon of material jam.If this is done for a long time, not only will the production efficiency be affected, the material attached to the jaw will corrode the jaw and accelerate its wear.
 



Solution for material with large water content:




Before the material enters the jaw crusher, the material is screened and prepared for dehydration to reduce the moisture and viscosity of the material.Dehydration can choose natural air drying air drying, or choose the configuration of drying equipment.



jaw crusher



2. The feeding amount is too large




In the production process of jaw crusher, some operators in order to speed up the production schedule, increase the amount of feed, beyond the normal production capacity of jaw crusher, materials in the crushing chamber can not be broken in time, resulting in stuck materials.
 



Solutions to excessive feeding:




Professional training should be given to operators to make them familiar with the knowledge of jaw crusher, so as to achieve continuous and stable feeding and effectively reduce the occurrence of material jam.
 



3. Improper adjustment of discharge port




The occurrence of material stuck phenomenon may also be because the discharge port is too small, the broken material can not be discharged in time, a large number of piles in the broken cavity, resulting in stuck material.
 



Solutions to improper adjustment of discharge port:




Adjust the outlet of jaw crusher properly, increase the size of outlet, so that the crushed material can be discharged from the outlet smoothly.



jaw crusher



4. Do not know the parameters of jaw crusher




Before use, there is no first clear jaw crusher parameters, especially the requirements of material properties.Material does not meet the requirements of the production process of jaw crusher, after entering the crushing chamber, it can not reach the ideal crushing effect, resulting in a decrease in production efficiency, resulting in material stuck phenomenon.
 



Do not understand the jaw crusher parameters solution:




Before using the jaw crusher for production, it is necessary to make clear the parameters of the jaw crusher, especially the requirements of material properties.According to the related requirements of jaw crusher for materials (such as size, hardness, etc.), put suitable materials.

Stuck material is a very easy phenomenon in the production process of jaw crusher, but as long as the cause is found, it is easy to solve the problem according to the correct method.



The page source:https://www.cementepc.net/company/Jaw-crusher-stuck-material-solution.html